2016-11-23 - Meeting notes

Participants

  • Laurent CLAUDE (Project Leader)
  • Matthieu HAZON (Developer)
  • Diana IBANESCU (Developer)
  • Jonathan MERCIER-GANADY (Developer)

Agenda

  • Work in progress: the first milestone

Minutes

  • The first milestone, the work done (please see the Redmine):
    • Auto-update
    • Mock-up
    • DataBase partially, still to do about architecture
    • Jenkins job for ubuntu 64b
    • Wrapper VMime, for ubuntu 64b
    • First draft for settings screen for email account
  • The milestone is delayed for 1 month: see you on December 21!
  • Proposal that everyone works mock-ups with Inskape. Matthieu will send us a draft.
  • Task #127:
    • is it possible to have library binaries in parallel than the Git repo?
    • Does Framagit manage the LFS?

Next Meeting

  • 2016-12-07